December 15, 2012

Sanitary sewer main increases size along E. Third Street

Pella — During last week's regular meeting, the Pella City Council approved a resolution for a Change Order on the E. Third Street Sanitary Sewer Project.

This resolution approves Change Order No. 2 with TK Concrete for the E. Third Street Sanitary Sewer Project in the amount of $14,659.55. As background, this project involves improvements on E. Third Street, between Peace and Independence, including: increasing existing sanitary sewer main from 12" to 21", replacement and additional storm sewer, installation of new 8" water main, new water and sanitary sewer services within the right-of-way, replacement of the street with 7" Portland Cement Concrete paving including both intersections, replacement of the 72" inch culvert for the street and 4' sidewalk replacement on both sides.

Details on the composition of Change Order No. 2 are:

-Removal of two old headwalls, hauling debris and reattaching an existing 15" storm sewer. In the past, this portion of E. Third was a rural area with an open ditch system. Headwalls provided additional support to keep the storm sewer pipe and road from moving or washing out. In this case, the original open ditch was tilled in and was completely eliminated many years ago, but the headwalls were never removed. Removal of the headwalls was important at this time to allow for the installation of the new 72" pipe and box culvert for increased capacity. Existence of these structures was unknown prior to construction: $10,034.56

-Removal and hauling of unexpected debris (railroad ties, brick, block, etc.) in the area of the old culvert: $2,312.94

-Upgrade of sanitary sewer services from planned 4" to 6" to match existing. This was due to a discrepancy between the plans based on the City records and what was actually found to be existing in the field. All sanitary sewer services were found to be 6" and not 4" pipe: $1,799.75

-Upgrade of water main service saddles from core blue to all brass: $512.30.The total addition to the contract for Change Order No. 2 is $14,659.55.

Text Only
Local News
Features
Facebook
AP Video
Rodents Rampant in Gardens Around Louvre House to Vote on Slimmed-down Bill for Border Looming Demand Could Undercut Flight Safety Raw: 2 Shells Hit Fuel Tank at Gaza Power Plant Raw: Massive Explosions From Airstrikes in Gaza Giant Ketchup Bottle Water Tower Up for Sale Easier Nuclear Construction Promises Fall Short Kerry: Humanitarian Cease-fire Efforts Continue Raw: Corruption Trial Begins for Former Va Gov. The Carbon Trap: US Exports Global Warming UN Security Council Calls for Gaza Cease-fire Traditional African Dishes Teach Healthy Eating 13 Struck by Lightning on Calif. Beach Baseball Hall of Famers Inducted Israel, Hamas Trade Fire Despite Truce in Gaza Italy's Nibali Set to Win First Tour De France Raw: Shipwrecked Concordia Completes Last Voyage Raw: Sea Turtle Hatchlings Emerge From Nest Raw: Massive Dust Storm Covers Phoenix 12-hour Cease-fire in Gaza Fighting Begins
Hyperlocal Search
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
Obituaries